Spread the love

Introduction

This article is a continuation on past articles and an extended discussion on the last post.
As a refresher, to build an effective and sustainable project management organizational system (PMOS), we presented our preferred approach, which is founded on three principles:

  1. Use a program management approach, in other words, treat the PMOS implementation initiative as a program rather than a project,
  2. Use an extended approach, meaning build the system over 1 to 3 years and not an intensive 3 to 6 months style,
  3. Follow the SUKAD Seven Elements of Project Management Maturity™ model (The 7Es™).
In the last post,  we re-touched on the 7Es™ and why an extended approach. Today, we will discuss: why do we propose the program approach?

Why the program’s approach?

  • Program sounds sexier than project:)
  • Program is more grandiose
  • Program is ‘strategic speak’

Seriously now!
There are three principal reasons:

  1. Extended approach with flexibility on time, accelerating or decelerating, and other factors make this more of a program rather than project with set deliverables and well defined time-frame.
  2. The organizational driver is for an initiative to enhance the organizational performance in managing the portfolio(s) – i.e. projects and programs; whether across the various functions or limited to a specific organizational unit. This situation makes a program approach as a better fit for such an initiative.
  3. A program approach allows us to set the program and strategic objectives, and then prioritize the various projects – on a case-by-case basis – to fit the organizational needs and expectations. Further, we can add or delete components on as needed basis.

It is worth noting that if the client chooses only a compressed implementation that could be well-defined, then we could have a project. On the other hand, if the client chooses the extended and staged approach, it would be best to treat this initiative, and the comprehensive engagement, as a program with multiple projects.

Possible program life cycle

Possible Program Life Cycle
In future articles we might discuss the details of the program but at this time we are keeping this confidential information.

Benefit of program management

We will try to explain using a graphic from a colleague and a PMI Fellow, Mr. Michel Thiry.
Benefit of Program Management in Organizational Change InitiativesWhat we understand from the diagram are:

  1. There are three horizontal dashed lines representing target situation, original situation, and minimum acceptable level.
  2. As an organization wanting to go from original to target situation, raise its performance level, it would need to implement new systems, policies, procedures, etc. Usually, that will have a negative impact in the early stage due to disruptions caused by the “change”, resistance to change, and the learning curve. This is shown in the line starting at the left axis and moving right and downward.
  3. If all the changes are implemented at once, sweeping organizational change, the large volume of new content, coupled with resistance to change, and learning-curve factor, the performance could continue to decline into the High Risk Zone, below the minimum acceptable level. This low performance will drag for a period of time before the performance starts to improve. Due to this situation and extended period in the high risk zone, there could be work disruptions, reduced motivation, losing trust in the system, and ultimately management might lose patience and abort the new system.
  4. Using a program management approach, with implementing smaller pieces of new work, there is time for assimilation and less resistance to change. Therefore, there is still a dip in performance but for a short time and will not likely go below the minimum acceptable level. Then there is an upswing since the team would have adopted the new process/system. This is what Mr. Thiry[1] calls a “period of relative stability”.
  5. With the recommended extended and staged approach, and with program management, we initially set up the high level system as an initial project. After a while, we come again to add a new project, new elements, and new learning. As the diagram shows, there will be a dip in performance for work related to the new elements, but possibly less severe than the earlier one.
  6. The process repeats over time until the organization reaches the target performance, and move on to continual improvement to sustain and move toward a center of excellence.

Basically, what we are saying is that through such an extended “program management” approach:

  • The resistance to change is significantly reduced since the change is gradual and in small segments,
  • The chance of success is higher, since the team has time to assimilate the learning, and
  • The organization is capturing and realizing the benefits, continually and with each project, instead of waiting to the end of the program.

Workshop on Building the Project Management Organizational SystemClosing remarks

What we are trying to present is how to build an effective and sustainable project management organizational system (PMOS), we presented our preferred approach, which is founded on three principles. Last time we discussed people-process-tools and extended staged approach. Today we discussed program management. In the next few articles,  we will go back to the maturity model and discuss in more details some of the content for each of the seven elements!


[1] Mr. Michel Thiry is PMI Fellow (highest honor by PMI®), the developer of the chart. He is also the author of an award winning book on program management.

Spread the love